Energomontaż The Winner - The Golden Website - V Edition Nagroda Ministra Skarbu Państwa dla Energomontaż-Południe SA Wyniki I etapu Konkursu ZŁOTA STRONA EMITENTA VI
HomeKontaktSite map HelpMobile versionPolska wersja językowa
You are here: Home » Experience » References
References

   Page 19 of 22   

 Year Client Scope of work
2004 COKE PLANT „PRZYJAŹŃ" SP. Z O.O. Complete overhaul of pressure absorption line No. B for No. 255 unit
2003 CEDLER STEEL MILL PHS SA Manufacturing of furnace hall's foundation and electro-energetic facilities
2002-2003 COKE PLANT "ZDZIESZOWICE" S.A. Erection of conveyor station No.4
2001-2002 ZEC BYDGOSZCZ Installation of 1K35 turbine set and auxilliares (for Alstom Power Elbląg)
2001-2002 COKE PLANT "ZDZIESZOWICE" SA Installation of dust removal system for the No. 7 coke battery
2001 SIERSZA POWER PLANT Installation and commissioning of LZS - 250.25/31.5 dumping and loading conveyor manufactured by Famak Kluczbork
2000-2001 POWER PLANT "DOLNA ODRA" SA Turn-key modernisation of compressor unit including delivery of three compressors Cooper Air Turbocompressor type TA 6000, capacity of 10, 000 m3/h each
2000 STEEL MILL HUTA KATOWICE SA Manufacture and assembly of concrete mixing installation
2000 ŁAZISKA POWER PLANT SA Turn-key modernisation of compressor unit including delivery of three compressors of Cooper Air Turbocompressor type TA 6000, capacity of 12, 000 m3/h each and modernization of three existing
2000 BĘDZIN SA HEAT AND POWER GENERATING PLANT Delivery, assembly and commissioning of 13 UCK 80 turbine set (Alstom Power)
1999-2000 SZCZECIN SA POWER PLANT Turn-key installation of 4 UCK 65 turbine set (Alstom Power)
1999-2000 RYAN NAMYSŁÓW BREWERY Installation of beer storage facility, modernization of degister house
1999-2000 SEJ SA PNIÓWEK COAL MINE Construction of integrated power generating - cooling plant for Pniówek Coal Mine
1999 ZEC MYSŁOWICE Turn-key installation of thermal degassing station
1998 JAWORZNO III SA POWER PLANT, POWER PLANT II Installation of 13 CK 70 turbine set and auxiliaries for power unit No. 3 (ABB Zamech)
1997-1998 SIERSZA SA POWER PLANT Erection of Flue Gas Desulphurisation Plant for power units 3 and 6 (award in the "Construction of the Year 1997" contest)
1997 JAWORZNO III SA POWER PLANT, POWER PLANT II Turn key installation of hot water pumping station, Vmax = 4200m3/h
1997 JAWORZNO III SA POWER PLANT, POWER PLANT II Construction of 13 CK 70 turbine set for power unit No. 2 (ABB Zamech)
2006 FLSMIDTH AIRTECH A/S Manufacture of electroprecipitator elements for Laappenranta unit (Finland)
2005 BIPROMET SA Assembly of electroprecipitator at funnel hall for Mittal Steel Poland SA (Dąbrowa Górnicza)

   Page 19 of 22   