1998 SEJ SA PNIÓWEK HEAT AND POWER GENERATING PLANT Delivery of flue gas ducts
1997-1998 SIERSZA POWER PLANT SA Installation of flue gas ducts (ø7500 mm) in flue gas desulphurisation plant
1997 RYBNIK POWER STATION Manufacture of flue gas ducts for FGDP
1997 SEJ SA MOSZCZENICA HEAT AND POWER GENERATING PLANT Replacement of flue gas ducts in OP 140 boiler
1997 ŁAZISKA POWER PLANT SA Removal, delivery and installation of flue gas ducts from fans to flue in No. 10 electroprecipitator
1996 ŁAZISKA POWER PLANT SA Removal and installation of flue gas ducts for No. 11 boiler
2005 PKE SA ŁAZISKA POWER PLANT Repair of No. 1 GAW rotor of Flue Gas Desulphurisation Plant (225 MW unit)
2004 PKE SA ŁAGISZA POWER PLANT Modernization of steam boiler OP 380 (reduction of NOx emission)
2003-2004 LOUGH REE POWER PLANT (IRELAND) Installation of Flue Gas Desulphurisation Plant for 100 MW power unit
2003-2004 WEST OFFALY POWER PLANT (IRELAND) Installation of Flue Gas Desulphurisation Plant for 150 MW power unit
2001-2002 ŁÓDŹ EC- 3 HEAT AND POWER GENERATING PLANT Assembly of NOx reduction installation of boiler OP 130 No. 1 and 2
2000 SIERSZA SA POWER PLANT Delivery and assembly of NOx reduction installation of boiler OP 380 No. 4
2000 ŁAZISKA SA POWER PLANT Assembly of Nox reduction installation of power unit 225 MW - 4 x OP-650 and 2x OP-380
1999-2000 ZOFIÓWKA HEAT AND POWER GENERATING PLANT Reduction of NOx emissions of boiler OP-140 No. 3 and 4
1998-1999 ŁAZISKA SA POWER PLANT Delivery and installation of flue gas desulphurisation plant of power units No. 11 and 12 (award in the "Construction of the Year 1999" contest)
1997-1998 SIERSZA SA POWER PLANT Principal Contractor of flue gas desulphurisation plant for power units No. 3 and 6 (award in the "Construction of the Year 1997" contest)
1997 RYBNIK SA POWER PLANT Delivery of equipment for flue gas desulphurisation plant
1996 ŁAZISKA SA POWER PLANT Installation of NID flue gas desulphurisation plant for power units No. 1 and 2
1995 POLMOS RACIBÓRZ Principal Contractor of flue gas desulphurisation plant (wet method)
2005-2006 COKE PLANT „PRZYJAŹŃ" SP. Z O.O. Complex modernization of Koksownia Przyjaźń Sp. z o.o. (coke plant) sewage-treatment plant.