Year | Client | Scope of work |
2005 | DESALINATION PLANT "DĘBIEŃSKO" CZERWIONKA - LESZCZYNY | Replacement and insulation of technological pipes (acid-resisting steel, ø > 1000 mm) |
2005 | PORĄBKA-ŻAR HYDRO-ELECTRIC POWER PLANT SA | Replacement of run-off cooling water pipelines of unit transformers and replacement of seal at suck pipes flaps |
2005 | ZUREC BĘDZIN SP. Z O.O. | Manufacture of gaseous-line No. 6 elements for corps frame of chamber agitator |
2005 | SEJ S.A. PNIÓWEK HEAT AN POWER GENERATING PLANT | Rebuilding of pipelines linking AKM and SKM refrigerating units |
2005 | DOLNA ODRA POWER PLANTS | Delivery and assembly of high and medium pressure pipelines of unit No. 8 for Alstom Power |
2003-2004 | HEAT AND POWER GENERATING PLANT ZOFIÓWKA SA | Delivery and assembly of live steam piping Ø 219 mm, Ø 159 mm |
2003 | HEAT AND POWER GENERATING PLANTS - ŁÓDŹ EC2 | Modernization of piping of heat generating turboset pipline TZ-7 |
2003 | PHS SA CEDLER STEEL MILL | Renovation of water pipeline (L= 400 m, Ø 490 mm), and assembly of natural gas pipeline (L= 150 m, Ø 200 mm) |
2003 | HEAT AND POWER GENERATING PLANT ZOFIÓWKA SA | Modernization of high pressure regeneration heaters' cooling system PWU 150 and PWU 200 |
2003 | GLIMAR REFINERY GORLICE | Prefabrication and assembly of Hydrokomplex piping system |
2003 | THE CITY OF TYCHY | Exchange of section of heat generating set in the Tychy |
2003 | OKOCIM BREWERY BRZESKO | Assembly of pipelines for heating water Ø 219 mm, demineralizated waterØ 108 mm and ammonia Ø 139 mm, Ø 50mm |
2003 | PKE SA ŁAZISKA POWER PLANT | Renovation of primary, live and feeding steam pipelines of turbo set No 9 |
2003 | PĄTNÓW POWER PLANT SA | Delivery of complete piping for turbine house of power unit A 460 MW (including P-91 grade) |
2002-2003 | TURÓW POWER PLANT SA | Manufacturing and delivery of complete piping for turbine house of power units No. 4 and 6 |
2002-2003 | PKE SA ŁAZISKA POWER PLANT SA | Modernization of large-size fittings and repair of low-pressure regeneration turbo sets TK-120 and TK-230 |
2002-2003 | EEG SUSZEC | Assembly of heating pipings housing estate |
2002 | MARICA POWER PLANT (BULGARIA) | Delivery of pipelines elements and turbine fittings 125MW |
2002 | RZESZÓW HEAT AND POWER GENERATING PLANT SA | Assembly of main steam pipelines (material P91)of steam-gas power unit 100 MW |
2002 | PKE SA JAWORZNO POWER PLANT | Delivery of high- and low-pressure pipelines within turbine 220MW No. 5 |