Year | Client | Scope of work |
1998 | COAL MINE DĘBIEŃSKO | Overhaul of centrifuges CWP 100/2K; SHS 602/715 2K; P-500/2 and compressors GTO - 98; SC-40 (Desalination Plant) |
1997 | PETROLEUM REFINERY JEDLICZE SA | Overhaul of 4VRK 150/280 turbo compressor |
1997 | NOWINY CEMENT PLANT IN SITKÓWKA | Dynamic measurement and assessment of eight 4VRK 150/280 compressors |
2006 | IKOMET ERTECH LTD. | Assembly of stacks for Mittal Steel Poland SA in Dąbrowa Górnicza |
2006 | KAEFER RACOENGINEERING GMBH | Manufacture of 2 pieces of stack systems with insulation |
2006 | KARRENA GMBH | Assembly and disassembly of stack in REG Raffinerie |
2003 | LEGNICA COPPER MILL | Manufacture of steel stack, H = 40 m |
2002-2003 | PAPER FACTORY FRANTSCHACH SA ŚWIECIE | Delivery and assembly of steel stack ø 2500 m, H = 100m |
2002 | JSW SA JAS-MOS COAL MINE | Disassembly of flue gas stack |
2001 | PKE SA JAWORZNO POWER PLANT | Manufacture of stack fittings (H = 300 m) |
1999 | ŁAZISKA SA POWER PLANT | Delivery and installation of steel ducts (ø 7600 mm) inside reinforced concrete stack (height 200 m) |
2006 | SEJ SA EEG SUSZEC | Manufacture and building of 2 pieces of tee on flue gas ducts |
2006 | FOSTER WHEELER FINLAND | Delivery and carriage of flue gas ducts to Italy |
2005 | ZEW KOGENERACJA SA (HEAT AND POWER GENERATING PLANT) | Manufacture, delivery and assembly of flue gas ducts to boilers OP-430 K-2 and K-3 |
2005 | SEJ SA MOSZCZENICA HEAT AND POWER GENERATING PLANT | Delivery and assembly of suction duct segment |
2005 | SEJ S.A. PNIÓWEK HEAT AND POWER GENERATING PLANT | Repair of flue gas ducts |
2005 | E.ON ANLAGENSERVICE GMBH | Delivery of flue gas ducts weighting 7.780 kg |
2003 | ZELSTOFF STENDAL | Manufacture of flue gas ducts Ø 1600 mm - 3740 mm for Stendal Cellulose and Paper Factory (Germany) |
2003 | FLSMIDTH AIRTECH A/S | Manufacture of flue gas ducts |
2003 | E.ON ANLAGENSERVICE GMBH | Manufacture of flue gas ducts for Power Unit of Marl Chemical Plant - block No. 312 and for Schkopau Power Plant - block AT |