08.06.2009
Energomontaż-Południe S.A. received an order for performance of assembly works on the high-pressure pipelines
On 4th June 2009 the Company received an order from Alstom Power Sp. z o.o. for performance of assembly works on the high-pressure pipelines (live steam, cold and hot re-superheated steam) in the wall-mounted, floor-standing and vertical part of the boiler at the "Bełchatów" S.A. power plant.
The value of the aforesaid investment task is approx. PLN 12.5 million net. The performance time shall fall on the period from 15th June 2009 to 30th November 2009.
Copyright © Energomontaż - Południe S.A.