Assembly of Flue gas and air ducts for Alstom

 

Alstom Power Systems GmbH order

Energomontaż-Południe SA shall assemble, for Alstom Power Systems GmbH, two sets of flue gas and air ducts for the coal-fired boiler operating in the 800 MW power unit at the Westfalen power plant in Germany.

The total value of the order shall amount to approximately EUR 16.83 million. The initially agreed date of commencement of the erection works shall be in February 2009, and the works are planned to be completed at the end of 2010.