Energomontaż-Południe SA with a new agreement worth PLN 28,9 milion


Energomontaż-Południe S.A. announces that on 24th January 2012 the Company signed an agreement with Alstom Power Systems GmbH on installation of auxiliary pipelines for the pressure component of a 910MW boiler in the Rheinhafen-Dampfkraftwerk power station in Karlsruhe. The agreement, valued at EUR 6.75 million (approximately PLN 28.9 million) is another package of work awarded to the Company to be carried out at the abovementioned site.

The individual parts of package 4 have various completion deadlines, however not exceeding 5th May 2012.