Current report no: 45/2009
Date: 12.08.2009
Conclusion of a contract with a design office - Biuro Projektów “Koksoprojekt" Sp. z o.o
The
Management Board of Energomontaż-Południe S.A. with its registered office in
Katowice (the Contractor/the Issuer/the Company) hereby announces that a
contract (the Contract) was concluded on 11th August 2009 between the Issuer
and Biuro Projektów "Koksoprojekt" Sp. z o.o. (Ordering Party), and
that the object of the contract is the performance of deliveries and the
assembly of deacidification and stripping columns in the area of the U.S. Steel
Košice s.r.o. Coking Plant, Slovak Republic. The value of the contract is EUR
2.55 million, the equivalent of PLN 10.7 million as of the publishing date of
this report. The task is going to be completed by June 2010. The final
acceptance inspection is expected to take place by the end of July 2010.
The contract provides for liquidated damages calculated on the basis of its value
and related to the failure to meet the deadlines for the following: project
delivery (1% for each week of delay that has started), equipment delivery
(0.05% for each day of delay), commissioning or removal of defects and backlog
with regard to acceptance inspection (1% for each day of delay), documentation
delivery (1% for each week of delay that has started). In case of faulty
performance of the Contract that cannot be attributed to the Contractor's
delay, the Ordering Party shall be entitled to charge liquidated damages from
the Contractor in the amount of 10% of the value of the Contract.
The Contract does not meet the "significant contract" criterion (equity as at the end of Q1 2009 amounted to approx. PLN 114 million), nevertheless the Company regards the contract as significant for its business due to the prospects related to the coking industry market segment.
The estimated value of the Company's order portfolio entailing the impact of the said Contract on the portfolio value is approx. PLN 468.7 million (the portfolio includes export orders in the amount of EUR 60.3 million), including the 2009 order portfolio of approx. PLN 272.7 (the portfolio includes export orders performed in 2009 for the amount of EUR 28.8 million). The value of the order portfolio for 2009 decreased as compared with the one published in current report No. 37/2009 of 10th July 2009 due to the delay in the completion of export contracts conducted in the German market for reasons independent of the Issuer. The portfolio value was calculated according to the EUR exchange rate the Issuer assumed for the order calculation.
SIGNATURES OF THE PERSONS REPRESENTING THE COMPANY
Andrzej Hołda | President of the Management Board |
Alina Sowa | Vice-President of the Management Board |
 
Legal grounds: article 56, paragraph 1, point 1 of the Act on offer - confidential information
 
Attachments:
Current Report No. 45/2009 | [pdf] 0,04 MB |
Copyright © Energomontaż - Południe S.A.